Which project management process is NOT likely to be used when resolving an issue?
- A. Change control
- B. Scope management
- C. Risk management
- D. Team building
Answer: D
NEW QUESTION # 240
Who are project team members primarily accountable to?
- A. The finance director.
- B. External stakeholders.
- C. The project manager
- D. The end users.
Answer: C
NEW QUESTION # 241
Which one of the following is NOT a project change?
- A. The potential for agreed resources to be removed from the project.
- B. An approved omission from the agreed project scope.
- C. A. requirement for extra expenditure to cover increased supplier costs.
- D. The removal of work packages from the agreed project scope.
Answer: A
NEW QUESTION # 242
In A. RACI coding format, what does 'A' stand for?
- A. Available.
- B. Accountable.
- C. Acceptable.
- D. Authorised.
Answer: B
NEW QUESTION # 243
Which of the following statements about scheduling is false?
- A. Considers work calendars and time contingency.
- B. Quantifies the required resources.
- C. Defines the sequence of activities.
- D. Provides a baseline for safety considerations.
Answer: D
NEW QUESTION # 244
Which one of the following is NOT typically associated with a project's context?
- A. The environment in which the project is being carried out.
- B. The issues and areas that matter to stakeholders.
- C. The sequence and dependencies of activities.
- D. Technical, social or political considerations.
Answer: C
NEW QUESTION # 245
One benefit of stakeholder analysis is that:
- A. the stakeholders can be removed from any of the decisions that are bang planned.
- B. the communication requirements for each stakeholder Can be established.
- C. the stakeholders who oppose the project the most can be "cut off' to reduce their negative influence.
- D. the communication plan becomes unnecessary.
Answer: B
NEW QUESTION # 246
How are outputs best described?
- A. The tangible or intangible products typically delivered by a project.
- B. The work packages developed in the W BS for the project.
- C. The realisation of benefits at the end Of the project.
- D. The changed circumstances or behavior that results from their use.
Answer: A
NEW QUESTION # 247
Which of the following is an activity in a typical risk management process?
- A. Justification
- B. Request.
- C. Verification.
- D. Closure.
Answer: D
NEW QUESTION # 248
The post project review report should be:
- A. archived for use in a future audit of project management processes.
- B. available to all project managers within the organisation
- C. restricted in circulation in case it contains critical information.
- D. included in the project plan for the next similar project.
Answer: B
NEW QUESTION # 249
Which one of the following best describes a project stakeholder?
- A. A party who has a vested interest in the outcome of the project.
- B. A party who is concerned about the project going ahead.
- C. A party who has a financial stake in the organisation managing the project.
- D. A party with an interest or role in the project or is impacted by the project.
Answer: D
NEW QUESTION # 250
Which of the following statements about the business case is true?
- A. The business case becomes the project manager's responsibility, once the project is in the implementation phase.
- B. The business case once written will never change.
- C. The business case contains key information on how the project will be performed.
- D. The business case should always be referred to throughout the project
Answer: D
NEW QUESTION # 251
Stakeholder analysis supports effective stakeholder engagement by:
- A. providing information to all stakeholders.
- B. identifying stakeholders with high levels of power and interest.
- C. ensuring stakeholder acceptance of project deliverables.
- D. justifying the preferred project option to stakeholders.
Answer: B
NEW QUESTION # 252
Which statement regarding the purpose of the business case would be the most true?
- A. It will act as a reference for the project team regarding the specific. processes to be used for project delivery.
- B. It will determine which stakeholders are most eligible to become members of the steering group,
- C. Once agreed the business case will become the baseline by which the project will be deployed,
- D. It will be referred to throughout the project in order to make decisions about the continuing viability of the project.
Answer: D
NEW QUESTION # 253
While providing support to the project and attending a risk management workshop, the following statements were noted. Which one of these could be considered as a risk to a project?
- A. We might not have sufficient people with the right experience to undertake the project.
- B. We have never worked in that country before.
- C. We always find that design verification takes longer than planned.
- D. We have never done a project of this kind before.
Answer: A
NEW QUESTION # 254
Which one of the following is captured in the Work Breakdown Structure (WBS)?
- A. The life cycle phases.
- B. The scope of the project.
- C. Project costs.
- D. The logical order of tasks.
Answer: B
NEW QUESTION # 255
Which of the following is true of the project environment?
- A. Only certain types of projects are influenced by the environment.
- B. The project environment will only really impact the project at the start.
- C. Within the environment are the factors that influence and impact projects.
Answer: C
Explanation:
D There is no real way of determining the true project environment.